Cork County Council has granted formal planning permission to Amazon Web Services (AWS) to construct a subsea cable landing station (CLS) in County Cork, Ireland, marking a significant milestone in the development of the company's first wholly-owned transatlantic subsea cable system, Fastnet.

The facility, approved on April 20, 2026, will serve as the eastern terminal for Fastnet—AWS's private subsea cable connecting Maryland, United States, to County Cork, Ireland. The cable system is scheduled to become operational in 2028.

Project Specifications: The Fastnet Cable System

Specification Detail
Cable Name Fastnet
Route Maryland, US (Eastern Shore) to County Cork, Ireland
Design Capacity Exceeding 320 Terabits per second (Tbps)
Owner/Operator 100% owned and operated by Amazon (via Amazon MCS Ireland Ltd)
Target Operational Date 2028 (Ready for Service)
Burial Depth Approximately 1.5 metres below seabed
Key Technology Optical switching branching unit for flexible routing

 

Fastnet Cable Route
Fastnet Cable Route, Image courtesy: AWS

 

The 320 Tbps capacity is capable of transmitting the entire digitised Library of Congress three times every second or streaming 12.5 million high-definition films simultaneously. The system will integrate directly into AWS's global network infrastructure, which currently spans 38 geographic regions and 120 availability zones connected by over nine million kilometres of terrestrial and subsea fibre optic cabling.

AWS has designed the cable with enhanced physical security measures, including burying the fibre approximately 1.5 metres under the seabed and adding extra armour plating near shore areas to protect against accidental damage or potential sabotage.

The Cork Cable Landing Station: Tullyneasky West

The newly approved facility will be constructed at Tullyneasky West, near Clonakilty, approximately 6 kilometres from Owenahincha beach where the cable will make landfall.

Infrastructure Component Detail
Location Tullyneasky West, near Clonakilty, Co. Cork
Site Preparation Demolition of two existing buildings
New Structures Cable landing station, ESB substation, switch room building, external plant infrastructure including generators and fuel tanks
Construction Timeline Expected to begin in late 2026; approximately one year duration
Developer Amazon MCS Ireland Ltd

West Cork Councillor Deirdre Kelly noted that the development would bring "improved digital infrastructure, increased connectivity and potential economic benefits, including local employment during construction and maintenance phases".

Councillors have confirmed that the Fastnet cable will not pass through the nearby Special Area of Conservation (SAC), addressing a key concern raised by local representatives and constituents during the planning process.

Strategic Rationale: Route Diversity

Amazon's decision to land the Fastnet cable in Cork represents a deliberate strategy to enhance network resilience. Most existing subsea cables landing in Ireland terminate in Dublin on the east coast, such as CeltixConnect-1, CeltixConnect-2 and EXA Atlantic, or on the west coast in Mayo (AEC-1, AEC-2 /Havfrue, AEC-3/Amitié) and Galway (IRIS, PISCES). Cork's only other major transatlantic cable, the EXA Express, has approximately one-sixth of the capacity of the new AWS Fastnet cable.

The Fastnet cable landing in Cork provides an "alternative pathway" for critical internet traffic in case of outages or disruptions affecting other transatlantic corridors. The system incorporates optical switching branching unit technology, positioned on the cable route to enable redirection of data to future landing points as network demands evolve.

AWS has stated that the system is specifically designed to handle growing AI traffic loads, which require substantial bandwidth for training large language models and processing machine learning workloads. The cable will feature automated network management tools that continuously monitor network health and automatically resolve 96% of network events without human intervention.

Community Investment and Local Impact

As part of the planning approval, Amazon has committed to establishing a Community Benefit Fund for the West Cork area, valued at approximately €150,000. The fund will support local initiatives including:

  • STEM education programmes in local schools
  • Environmental sustainability projects
  • Health and wellbeing services
  • Educational and workforce development programmes
  • Local community group initiatives

Councillor Isobel Towse confirmed that local representatives "managed to secure a much more substantial figure for a community fund than what was previously offered" during negotiations with Amazon.

Ireland as a Digital Gateway

Taoiseach Micheál Martin welcomed the project upon its announcement in November 2025, stating:

"Amazon's new Fastnet transatlantic subsea cable represents a vote of confidence in Ireland's digital future, helping to enable the next wave of innovation in cloud computing and AI. By linking County Cork to Maryland in the United States, Ireland will become a true gateway to Europe for submarine telecommunications cables".

Maryland Governor Wes Moore similarly hailed the project as securing "Maryland's status as a global hub for innovation, job creation and high-tech investment" while noting that this represents Maryland's first subsea fibre cable landing.

Regional Context: Cork's Subsea Hub Status

Cork is rapidly emerging as a strategic subsea connectivity hub. Two other major infrastructure projects are currently active in the region:

Project Type Route Status
PISCES Subsea telecommunications cable Ireland (Galway) to Portugal, Spain, France Announced March 2026; EU co-funded
Celtic Interconnector Electricity interconnector (700 MW) East Cork to Brittany, France Under construction; €1.6 billion; targeted for 2028 launch

The Celtic Interconnector, which will become the world's longest XLPE subsea interconnector at 575 kilometres, has received over €530 million in EU grants and is recognised as a Project of Common Interest by the European Union. Construction on the project began in 2023, with cable-laying operations currently underway off Ireland's southeast coast.

Industry Implications

For the subsea cable industry, Fastnet represents a continuation of the trend where hyperscalers—Amazon, Google, Meta, and Microsoft—are moving from capacity leasing arrangements to full ownership of subsea infrastructure. This vertical integration provides:

  • Cost predictability through elimination of third-party capacity fees
  • Strategic control over routing and landing point selection
  • Capacity assurance for AI and cloud workloads
  • Route diversity to enhance network resilience

The 2028 operational date aligns with expected completion of Amazon's broader infrastructure expansion, including three new AWS Regions and ten additional Availability Zones currently in development.

Next Steps

With planning approval secured from Cork County Council, the project now advances to the next regulatory phases. Amazon will apply to the Maritime Area Regulatory Authority (MARA) for a Maritime Area Consent (MAC) to occupy part of the seabed. Following MAC approval, the company must apply to An Coimisiún Pleanála for planning permission to install the cable itself.

Construction of the cable landing station is expected to begin in late 2026, with completion targeted for 2027, ahead of the cable system's planned 2028 Ready for Service date.